Network infrastructure in an office move: the IT plan, phase by phase

When moving premises, the network is decided before the works. Long lead times, decisions that cannot wait, a phased plan and the mistakes that keep repeating.

Updated 17 October 20263 min readDataRoad - IT Services and Consulting

At a glance

For decision-makers short on time.

  • 01Network decisions must be made before walls and ceilings close; afterwards every change is destructive.
  • 02The internet connection has the longest lead time: confirm fibre coverage before signing the lease.
  • 03Test everything with the space empty, never move on a Friday and keep the old office for a few days.
In this article
Mudança de escritório: checklist informático por fases para não falhar no novo espaço da empresa — DataRoad

When moving premises, network infrastructure decisions must be made before the building works start: once walls and ceilings are closed, every change is destructive. The item with the longest lead time is the internet connection, which should be confirmed before you even sign the lease. And a move is the only opportunity to rebuild the network from scratch with no additional building cost. This is the plan DataRoad - IT Services and Consulting follows with its clients.

Why the network is usually left until last — and what that costs

In most moves, IT comes in after the lease, the fit-out and the furniture. The result is weeks of working badly in the new space: outlets in the wrong place, weak Wi-Fi, temporary internet. The right order is the reverse.

The two lead times money cannot buy

  • Internet connection — bringing fibre to a building that does not have it involves infrastructure, permits and sometimes street works. It can take weeks or months. Confirm coverage before choosing the space and place the order on the day you sign.
  • Number porting — it has legal deadlines and depends on the losing carrier. Starting late means moving without the numbers your clients know.

An excellent space with no fibre available has forced companies to work for months on inadequate temporary connections.

Decisions to settle before the works

  • Rack Space, ventilation, dedicated power sockets and security. A cupboard in the corridor with no ventilation is paid for in failures for years.
  • Network outlets Count today’s headcount and add a margin. Extra outlets during the works cost little; too few afterwards means more building work.
  • Cable routes Cable trays and routes agreed with the contractor, not improvised.
  • Business Wi-Fi Access point positions come from a wireless coverage survey on the floor plan, with cable to each point, including ceilings and high areas.
  • Power A dedicated circuit for the rack and space for a UPS.
  • CCTV and access control They use the same cabling and belong in the same project.

DataRoad IT Unlimited

Talk to DataRoad. We assess your operation and propose the right plan.

Request a proposal →

A phased IT plan

StageWhat to do
Space chosenConfirm and order internet; start number porting; inventory what exists and what is moving.
Before the worksStructured cabling design with an outlet plan; rack location; coordination with the electrician and contractor.
During the worksRun cable before ceilings and walls are closed; install the rack; certify the network with a per-outlet report.
Two weeks beforeInternet installed and tested; network, Wi-Fi and phone system configured; everything tested with the space empty.
Moving weekTransport plan for servers and equipment; shutdown and start-up order; emergency contacts for all suppliers on a single sheet.

Three rules for moving day

  1. Never on a Friday — a problem discovered late in the afternoon lasts the whole weekend. Move early in the week, with suppliers reachable.
  2. Test before people arrive — servers, network, internet, phones and printers validated with the space empty. Discovering a fault with forty people waiting is the worst-case scenario.
  3. Keep the old space for a few days — being able to fall back for a week is worth the cost; it is rarely used, but it changes everyone’s peace of mind.

Mistakes we see in almost every move

  • Inherited, uncertified cabling The previous tenant’s cabling may be fine or unusable. Certifying it before deciding costs little.
  • Sizing for today Companies that move premises are usually growing. Planning for current headcount books the next building project already.
  • Forgetting peripherals Printers, time clocks and meeting room equipment always turn up at the end, with no outlet planned.
  • IT left out of site meetings That is where cable routes and the rack location get lost.
  • Installation without documentation Without a floor plan and outlet map, the first fault begins with guesswork.

Next step: plan the network for your new office

DataRoad handles office moves and business network installation from start to finish — from the design with the contractor to validation on the first working day. No-obligation proposal.

More than 10 workstations · support contract · remote, on-site and telephone support

DataRoad · IT Services and Consulting

One StepAhead of IT.

Portugal’s premium IT brand for international companies: one partner, one contract and one security standard for every office, in Portugal, Europe and the US.

  • 232clients in Portugal and abroad
  • PT · EU · USremote and on-site support
  • 5,052 Google reviews

We do IT right.

DataRoad IT Unlimited

Want a network and IT that simply work?

Talk to DataRoad. We assess your operation and propose the right plan.

Request a proposal, no commitment →+351 211 459 950**Call to a Portuguese landline · More than 10 workstations · support contract · remote, on-site and phone support